Turnaround (TAR) planning, from scope call to post-TAR review
Safety: Educational overview only. Always follow your site's procedures, permits and applicable regulations.
Est. 0.5 h · estimated
A turnaround is a planned outage to do work that can't be done while the unit runs. This page covers the generic timeline, how to screen scope, how to triage work found during the outage, and how TAR work is handled in SAP PM.
TAR lifecycle timeline
- T-36 → T-24
- T-24
- T-18
- T-16 → T-12
- T-24 → T-3
- T-12 → T-6
- T-9 → T-4
Estimate & contractor packages
Rough estimate (T-9), contractor bid packages by scope (mechanical, I&E, specialty), then approval estimate (T-4) [T2].
- T-6 → T-3
Schedule integration
Export orders and operations to MS Project or Primavera P6; build shutdown, execution and startup logic; critical path; resource-level by craft; lock schedule by about T-3 [T5].
- T-6 / T-3 / T-1
- T-0
- T+0
- T+1 → T+3
Scope screening criteria
Requires the unit down
Cannot be done safely or physically while running (vessel entry, exchanger pulls, isolation not possible online).
Safety / regulatory
Inspection due dates, SIS proof tests that can only be done offline, permit or code commitments.
Reliability / risk
Known degradation or bad actor that would cause an unplanned outage before the next window.
Economic / capital
Approved project tie-ins and improvements with funding (WBS / investment order).
Ready to plan
Clear scope, technical object identified, engineering complete, long-lead materials orderable in time.
Not TAR scope
Can be done online, has no reason to be in the outage, or is not funded / engineered: keep in routine backlog.
Criteria are illustrative
Emergent / discovery work triage
TAR handling in SAP PM
1Group TAR work with a revision
A revision (maintenance revision) is a time window on a planning plant. Each TAR order is tagged with the revision in the order header so the whole outage can be filtered, reported and scheduled together.
2Filter the TAR worklist
Use the order list with the revision selection to pull every TAR order for planning status, readiness and cost reviews.
3WBS-based TARs
Some sites run the TAR as a project: a WBS per area or package, with orders assigned to WBS elements for budget and cost tracking.
4Export to scheduling tools
Orders and operations (hours, work centers, dates) are exported to MS Project or Primavera P6 for logic and critical path, then dates and progress are brought back. Method varies: report export, interface or add-on.
5Capacity & materials
Check craft loads against contractor headcount; track TAR material reservations and long-lead purchase requisitions.
- Order
- 4000510 PM01
- Description
- E-201 Example Exchanger: pull bundle, hydrotest
- Planning plant
- 1000
- Revision
- TAR26
- Revision period
- 2026-04-06 → 2026-04-27
- Main work center
- MECH-01
- WBS element
- TAR-2026-U100
CRTDUser statusTAR- CRTD
- REL
- PCNF
- CNF
- TECO
- CLSD
Revision field location and user status TAR are examples
- Revision
- TAR26
- Planning plant
- 1000
- Order type
- PM01, PM02
| Order | Rev. | Equipment | Description | Status | Ready |
|---|---|---|---|---|---|
| 4000510 | TAR26 | E-201 | Pull bundle, hydrotest | REL | ✓ |
| 4000511 | TAR26 | P-101 | Overhaul pump, new seal | REL | ✓ |
| 4000522 | TAR26 | PT-101 | SIF proof test, calibrate | CRTD | Mat. pending |
| 4000530 | TAR26 | V-300 | Internal inspection | CRTD | Permit pending |
CRTDREL- CRTD
- REL
- PCNF
- CNF
- TECO
- CLSD
Selection by revision TAR26
Typical TAR scope · Mechanical
Heat exchangers
Bundle pull, clean (hydroblast / chemical), tube inspection (eddy current / UT on critical service), tubesheet and baffle checks, plug or retube, hydrotest, new gaskets [V10].
Columns / towers
Open, clean, tray-by-tray inspection numbered from the drawings: deposits, corrosion, cracks, stuck or missing valves, downcomers, seal and draw pans; punch list before box-up [P3].
Pressure vessels & drums
Internal inspection and NDT by the inspection group (API 510 basis), internals and demister repair, fitness-for-service where degraded, box-up inspection sign-off [V11].
Relief valves (PSVs / PRVs)
Remove, bench test (as-found set pressure), overhaul seat / spring / guides, reset, re-test, tag and reinstall with records; inlet / outlet line checks (API RP 576 basis) [P4] [V11].
Pumps
Overhaul of pumps that cannot be isolated online: seals, bearings, wear rings, impeller, alignment and as-left vibration baseline.
Rotating equipment overhauls
Compressor and turbine overhauls (often OEM-supported): rotor inspection, bearings, seals, governor/trip checks; long lead for rotors and parts.
Piping & valves
Piping inspection / replacement (API 570 basis), block valve repair or replacement, blinds list and flange management, bolting to spec [V11].
Typical TAR scope · I&E
SIS / SIF proof tests
End-to-end tests (sensor → logic → final element) including trip points, alarms and valve response, for functions that can only be tested offline. Record every fault, even a small calibration error (IEC 61511 basis) [P2] [V9] [V8].
Analyzers
Analyzer and sample-system overhaul, calibration and validation; gas detectors calibration [V8].
Control valve overhauls
Walk-down with diagnostics and as-found photos, then repair vs replace; trim, packing, seat rings, actuator; stroke test and diagnostics after repair [V7] [V8].
Transmitter calibration
Pressure, flow, level and temperature calibration with as-found / as-left records; replace failed devices [V8].
MCC / switchgear PMs
Electrical equipment that needs the unit or bus de-energized: cleaning, torque checks, IR thermography follow-up, protective relay testing, breaker maintenance (NFPA 70B basis) [P6].
Loop checks & function tests
Loop checks after any instrument or wiring work, interlock function tests, and startup verification before handback [V8].
Criticality shown is illustrative; your site risk matrix governs
Work package contents checklist
Built from [V3] [V4]. Use it as the completeness check before a package is marked ready.
- LowHeader Order number, equipment / functional location, revision, priority, craft, estimated hours and crew size
- MediumScope of work Clear step-by-step job plan with sequence and access
- MediumDrawings & documents P&IDs with job location marked, isometrics, vendor manuals, loop drawings, datasheets
- MediumBill of materials Parts, gaskets, bolting, consumables with stock / PO status and kit location
- LowTools & equipment Special tools, cranes and rigging, test equipment with calibration
- HighSafety JHA, PPE, permits (confined space, hot work), isolation / LOTO and blind list
- HighMOC MOC reference for any change in design, setpoint or SIS; field change handling
- HighQuality QC hold points, torque specs, tolerances, test and inspection requirements
- MediumTie-ins Tie-in numbers and tags matched to the job (capital work)
- LowCheck & punch list Package completeness checklist and punch list for close-out
Readiness review checklists
Gate reviews end in Go, conditional Go with owners and dates, or Hold [V5] [V6]
T-6 review
- MediumScope frozen; LWR process running and tracked
- HighWork packages: high-risk packages complete and reviewed
- MediumLong-lead materials: POs issued, delivery dates confirmed
- MediumContractor strategy and packages awarded
T-3 review
- MediumSchedule logic and critical path approved; resource-leveled
- MediumAll work packages complete and signed
- HighPermit and isolation plan, blind list, isolation matrix
- MediumCritical spares and kits confirmed in stores
- HighSIS proof-test procedures current and approved
T-1 review
- HighContractor competence, inductions and rosters confirmed
- MediumMaterials kitted and staged by package
- LowPre-TAR work done (staging, prefab, online prep)
- HighEmergency response, PSSR and startup plans approved
- MediumGo / conditional Go / Hold decision recorded with owners
TAR KPIs
| KPI | Formula | Example target | Weight |
|---|---|---|---|
| Schedule compliance / critical path adherence | Critical-path activities done on time ÷ total critical-path activities | e.g. > 85% [V2] | Medium |
| Schedule performance | Actual duration ÷ planned duration (shutdown to startup) | e.g. 0.95–1.05 [V2] | Medium |
| Scope growth | Approved scope added after freeze ÷ frozen scope (hours or cost) | Track trend; site target | Medium |
| Emergent / discovery work % | Discovery work cost ÷ total actual cost | e.g. < 12% [V2] | Medium |
| Budget (cost performance) | Actual cost ÷ approved budget incl. contingency | e.g. 0.95–1.05 [V2] | Medium |
| Late Work Requests | Number, value and approval time of LWRs by requesting group | Downward trend [T3] | Low |
| Time-on-tool / wrench time | Productive hours ÷ paid hours | e.g. > 50% [V2] | Low |
| Safety | Recordable incident rate during the event | Zero harm; site target | High |
| Startup | Stable operation without rework shutdown after startup | First-time success [V2] [T6] | High |
Example targets are from a vendor benchmark page and are not industry standards; set your own baseline . Broader TAR performance measures: [T6]
Roles · RACI
| Activity | TAR manager | Planner | Scheduler | Ops rep | Inspection / reliability | Contractor |
|---|---|---|---|---|---|---|
| Scope call & challenge | A | R | I | C | C | I |
| Work package build | A | R | C | C | C | C |
| Materials & long-lead | A | R | I | I | C | I |
| Schedule & critical path | A | C | R | C | I | C |
| Readiness reviews | A | R | R | C | C | C |
| Emergent work triage | A | R | C | C | C | I |
| Daily progress & updates | A | C | R | I | I | R |
| Closeout & lessons learned | A | R | R | C | C | C |
R = responsible, A = accountable, C = consulted, I = informed. Generic example; materials/stores, and inspection vs reliability split, vary by site
Post-TAR closeout
- MediumConfirm all labor and close operations IW41 / IW44 time and final confirmations; check no open operations remain.
- MediumComplete notifications with codes Damage, cause and activity codes; findings recorded for history.
- MediumTECO orders Set technically complete via IW32 / IW38 mass change; clear open reservations.
- LowReturn or reserve surplus material Return unused kitted parts; restock or scrap per site rules.
- HighClose MOCs and update records Drawings, SIS documentation, PSV records, equipment data updated.
- LowSettle and close Settle costs (KO88 / project settlement), business-close after invoices.
- LowFinal cost report Cost by package and category vs budget, around T+3 [T2].
- MediumPost-TAR review Within about two months: KPIs, lessons learned, carry-over and deferred scope into the next TAR list [T1].
Lessons-learned template
| Field | Entry |
|---|---|
| Event / unit and date | |
| Category: scope, planning, materials, schedule, contractor, safety, startup | |
| What happened (facts, order / package reference) | |
| Impact: hours, cost, days, safety | |
| Root cause | |
| What worked (keep doing) | |
| Recommendation for next TAR | |
| Owner and due date | |
| Where it lands: task list, work pack template, scope list, spares | |
| Status: open / in progress / closed |
Capture during execution, not only at the review [T7] [V1]
Follow one order through every stage on the work order lifecycle page.
Sources (25)
P = standard, regulator or peer-reviewed · T = trade press · V = vendor or consultant (secondary). Linked for further reading; this page summarizes, it does not reproduce them.
- [T1] BIC Magazine, "Quality work scopes imperative for turnaround success" (T) T-minus milestones (T-32, T-24, T-18, T-16 freeze), post-TAR review within ~2 months
- [T2] IAMTech, "Turnaround Best Practices" (V) T-minus funding/estimate gates (T-36, T-24, T-12 freeze, T-9 ROM, T-4 AFE, T-0.5 control budget, T+3 final cost report), change-order mindset
- [T3] BIC Magazine, "Scope management impacts on turnarounds" (T) Premise document, scope submittal/challenge, scope freeze 6–12 months, Late Work Request (LWR) contents and tracking
- [T4] The Chemical Engineer, "Controlling Your Maintenance Turnaround Scope, from Kick-Off to Closeout" (T) Premise, steering team role
- [T5] Oxmaint, "Shutdown and Turnaround Maintenance Planning" (V) Six-phase lifecycle, T-6 planning complete, T-3 schedule locked
- [P1] UKZN research thesis, "The impact of scope changes on turnaround schedule and cost in the Oil Refinery Industry" (P) Known / anticipated / emergent scope types; scope change after freeze drives delay and cost
- [T6] A. H. Ragab, IQPC STO Middle East 2015, TAR performance measurement (T) TAR performance criteria (duration, cost, predictability, safety, startup incidents, additional work vs contingency)
- [V1] Matterport, "Refinery Turnaround Planning: 4 Best Practices" (V) Five phases, pre-TAR readiness (scaffold, prefab, staging), post-TAR review contents
- [T7] K. Hooshvar, Project Controls Expo USA 2024, "Navigating Project Controls in Refining" (T) Lesson learned: earlier scope freeze, sign-off and tracking of added scope
- [V2] iFactory, "Turnaround Performance Benchmarking & KPIs" (V) KPI formulas and example targets (CPI, SPI, discovery %, time-on-tool, change order rate, critical path adherence, first-time startup)
- [V3] STO Control (Cleopatra), "7 essential items of a Turnaround Work Package" (V) Work package contents (SOW, P&IDs, drawings/BOM, MOC, safety, tie-ins, check & punch list)
- [V4] F7i, "Maintenance Shutdown Planning Checklist" (V) Scope inputs (PM/PdM, CM backlog, inspection, capital, requests); work package checklist (header, steps, JHA/LOTO/permits, BOM, tools, drawings, QC hold points, labor)
- [V5] beefed.ai, "Turnaround Readiness Gates Checklist" (V) Gate dimensions: safety, scope, spares, competence; PSSR, MOC closure, kitted work packs
- [V6] beefed.ai, "Turnaround Readiness Review: 7-Step Audit" (V) Readiness checklist domains; Go / conditional / hold decision
- [T8] Hydrocarbon Processing, Feb 2024, Benomar, Turnaround/Project Mgmt (T) Materials readiness questions (POs issued, deliveries on track, contracts in place, contingencies)
- [V7] Emerson Instrument & Valve Services catalog (turnaround process) (V) Control valve walk-down (as-found photos, serials), parts pre-order (packing, gaskets, seat rings, trim), master tag control log
- [V8] BBP, Field Services (V) I&E TAR scope list: loop checks, calibrations (incl. analyzers, gas detection, vibration), interlock and SIS/SIL testing, valve stroke/partial stroke, diagnostics
- [P2] ISA-TR84.00.03 preview, "Guidance for Testing of Process Sector SIFs" (P) SIS proof testing rationale (dormant failures)
- [V9] Covol Engineering, "A Guide to Proof Testing" (V) End-to-end proof tests incl. settings and trip points; test intervals vs shutdown periods; record all faults; IEC 61511 benchmark
- [P3] AIChE CEP, "Inspecting Distillation Towers Part 1: Turnarounds" (Sep 2018) (P) Column tray inspection steps: number trays, cleaning, damage/missing hardware, punch list
- [P4] API RP 576, "Inspection of Pressure-relieving Devices" (preview / table of contents) (P) PSV/PRV inspection, testing, causes of improper performance, records
- [V10] POPProbe, Refinery Turnaround and Inspection Planning checklist (V) Exchanger bundle scope (tubes, tubesheets, baffles; ECT/UT; cleaning; spare bundles)
- [V11] POPProbe, Refinery Unit Turnaround Safety Inspection (V) MI verification: API 510/570 inspector review, NDT, PSVs tested, internals documented before box-up, correct gasket/bolt/seal materials
- [P5] OSHA 29 CFR 1910.119, Process Safety Management (P) PSSR, MOC, mechanical integrity
- [P6] NFPA 70B, Standard for Electrical Equipment Maintenance (P) Electrical equipment (MCC/switchgear) maintenance basis