Notifications and Work Orders
Module 1 Est. 3 h · estimate · draft
You'll be able to
- Tell a notification from an order
- Review the operations a task list copied into an order
- Apply Palmer's view of labor estimates
Why it matters in the plant
The planner's review of each order is where planning adds value: right crafts, right hours, and history checked.
In this lesson
- Handle notifications and orders
IW21IW22IW23IW31 - Review the operations copied from the task list
IW32 - Adjust the plan using history and judgment
IW32IW39
Common mistakes
- Editing the routine PM order to cover a corrective finding: raise a notification and a separate order instead [S11].
- Trying to make every estimate perfect: across a week's batch, the total often lands within about 15% [S19].
Steps and transactions
Each step pairs the planning work with the transactions you'll use. Codes link to the reference.
1Handle notifications and orders
A notification brings a problem or request into the system. Create it with IW21. Create orders with IW31 and change them with IW32. A PM order usually comes from the plan. A finding on a route becomes a notification, then a separate corrective order.
Craft notes
Mechanical: a high vibration reading on the pump becomes a notification, then a corrective order.
Sources [S11] SAP Learning, Creating Orders; [S3]
2Review the operations copied from the task list
Specify the task list and dates, and the operations are copied over. Each operation carries a work center, work hours, duration, number of people and a control key.
Craft notes
Mechanical: a mechanical work center for seal and alignment work, and possibly a separate one for vibration (illustrative Unverified). I&E: an instrument work center for calibration and the proof test.
Sources [S3]; [S11]
3Adjust the plan using history and judgment
Planning prepares future work, using history kept at the component level and labor estimates based on the planner's judgment. A single job's estimate can be off by as much as ±100%, but a week's batch of work often lands within about 15%. A candidate transaction for reviewing history is IW39, Display PM Orders list [map E] Unverified.
Craft notes
Same principle for both crafts.
Sources [S17] Palmer, Purpose and principles; [S19] Palmer, Math of planning
Templates for this lesson
Downloadable task list / plan templates for this lesson will appear here. [Owner to supply]
Related: Complete template bundle · Free PM Planning Checklist
Check your understanding
Questions and answer key
- A route finds high vibration. What should the planner do?
- Individual estimates can be off by ±100%. About how close does a week's total land?
- What does each copied operation carry?
Answer key
- Create a notification, then a separate corrective order [S11]
- Within about 15% [S19]
- A work center, work hours, duration, number of people and a control key [S3][S11]
Interactive scoring and certificate tracking come with student accounts (see the dashboard preview).