Courses / Module 1 / Scheduling
Capacity and the Weekly Schedule
Module 1 Est. 3 h · estimate · draft
You'll be able to
- Check work center capacity against load
- Build a fully loaded weekly schedule using Palmer's six principles
Why it matters in the plant
A fully loaded, prioritized weekly schedule is what turns good planning into completed work.
In this lesson
- Check capacity
IW37NCM01CM25 - Build the weekly schedule
IW37N
Common mistakes
- Loading the schedule below 100%: work expands to fill the time (Parkinson's Law) [S18].
- Using CM01 alone to judge PM load: it doesn't show order-header capacity requirements (Note 385059) Unverified.
Steps and transactions
Each step pairs the planning work with the transactions you'll use. Codes link to the reference.
1Check capacity
Each work center has a defined capacity, with shifts and utilization. CM25 levels operations against capacity; this detail comes from a search summary of [S16] Unverified. CM01 (work center load) is confirmed, with a caveat: per SAP Note 385059, as cited on SAP Community, CM01 does not show the capacity reserved by a maintenance order's header dates. Those requirements show in CM21/CM25/CM50, and PM load is normally checked in CM25 or CM50 Unverified. Candidate: IW37N, Change Orders and Operations [map E] Unverified.
Craft notes
Mechanical and I&E work centers are checked separately.
Sources [S16] SAP Learning, Configure Work Centers; KBA 2587998 and SAP Community (CM01), per reference-library.md §4
2Build the weekly schedule
Palmer's six principles: (1) job plans identify craft skill and labor estimates; (2) a credible priority system; (3) the next week is the scheduling horizon; (4) that week's forecast is loaded to 100%; (5) field supervisors handle daily scheduling; (6) schedule compliance is measured. Example: 10 mechanics × 40 h = 400 h available, so schedule about 400 h, starting with priorities and bundling work by area or asset. Fernandina Beach, FL went from about 170 to 225 work orders a week by raising loading from 80% to 100%. Candidate: IW37N, with Fiori F4073 Manage Maintenance Backlog (S/4HANA only, not ECC Unverified) Unverified.
Craft notes
I&E: schedule the transmitter test together with operations because of the bypass.
Sources [S17]; [S18] Palmer, Fully loaded weekly schedule
Templates for this lesson
Downloadable task list / plan templates for this lesson will appear here. [Owner to supply]
Related: Complete template bundle · Free PM Planning Checklist
Check your understanding
Questions and answer key
- A crew of 10 works 40 h with no time off. How many hours should you schedule?
- What is the scheduling horizon?
- Why isn't CM01 enough for checking PM load?
Answer key
- About 400 [S18]
- Next week [S17]
- It doesn't show the capacity reserved by order header dates; use CM25/CM50 (reference-library §4) Unverified
Interactive scoring and certificate tracking come with student accounts (see the dashboard preview).
Discussion
Questions and answers from other planners will appear here once student accounts exist. Moderation approach: [TBD by owner].
How do you set the call horizon for a 6-month package on a SIF transmitter?